Client
WRW
Project
Value – £800,000
Duration – 6 months
Description
Complete electrical installation and commissioning of all lighting, power, fire alarm and emergency lighting systems.
Works carried out:
- Installation of 730KVA Generator
- Installation of 160KVA UPS back up system
- Installation of 1250Amp MCCB panel
- Installation of a full LV distribution system including split lighting/power distribution boards and metering to conform to the latest Part L requirements.
- Installation of Dali networked lighting control system.
- Installation of Lighting, Emergency lighting to conform to BS5266 and external lighting.
- Installation of Structured cabling system.
- Installation of LV power including floor boxes, dado trunking and UPS backed circuitry.
- Installation of a fully addressable fire alarm system through out the building.
- Installation of a fully IP based CCTV system
- Installation of a fully integrated Access control system
- Commissioning of all systems